In coordination with Parker County and the Texas Department of Transportation, this locally initiated project will provide for improved traffic flow at the US180/IH-20 interchange. The Hudson Oaks Bridge will be widened from 2 lanes to 4 lanes; the US-180/Hudson Oaks Drive intersection will be expanded and reconstructed in concrete; and the frontage road at IH-20/Hudson Oaks Drive will have signals installed.
The City is responsible for engineering and, along with Parker County, a small portion of the construction costs. TxDOT is providing construction management and the majority of construction costs.
In addition, Green Ribbon funding for new IH-20 landscaping was added to this project after it was awarded to the contractor.
Project Images
Project Updates
May 4, 2018
The contractor is currently addressing final punch list items. Completion for this project is expected to be declared in the coming weeks.
July 14, 2017
The intersection at US 180 and Hudson Oaks Drive is expected to be completed later this month. Additionally, an agreement has been reached with TxDOT to include the Green Ribbon (IH-20 Vision) project into the Hudson Oaks Bridge project.
September 19, 2016
Major bridge and highway closures are planned for this weekend. The closures will occur during the evening on Thursday, Friday, and Saturday nights. An informational site has been created that provides information on these and future closures in Hudson Oaks. You may view the site at http://road-closures.hudsonoaks.com.
May 5, 2016
As of this morning, the City Council has officially changed the name of a portion of Lakeshore Drive to "Hudson Oaks Drive." The change impacts the portion of the road from the IH-20 frontage road to Inspiration Drive. Hereafter, this project will be referred to as the Hudson Oaks Bridge project. Signage and barricades will begin being placed later this week.
May 5, 2016
Notice to proceed has been issued to the contractor. A pre-construction meeting will be held soon, with construction expected to begin promptly thereafter.
September 2, 2015
Right of way acquisition is now complete.
May 2016
Start Date
May 2018
Expected Completion
$7.2m
Contract Value
2007 CO, 2016 CO
Funding Sources
Ed Bell Construction
Contractor
City of Hudson Oaks
Parker County
Texas Department of Transportation
Project Partners